<?xml version="1.0"?>
<feed xmlns="http://www.w3.org/2005/Atom" xml:lang="en">
	<id>https://uww.wfgnationaltitle.com/index.php?action=history&amp;feed=atom&amp;title=Construction_Liens_in_North_Carolina</id>
	<title>Construction Liens in North Carolina - Revision history</title>
	<link rel="self" type="application/atom+xml" href="https://uww.wfgnationaltitle.com/index.php?action=history&amp;feed=atom&amp;title=Construction_Liens_in_North_Carolina"/>
	<link rel="alternate" type="text/html" href="https://uww.wfgnationaltitle.com/index.php?title=Construction_Liens_in_North_Carolina&amp;action=history"/>
	<updated>2026-05-15T12:21:02Z</updated>
	<subtitle>Revision history for this page on the wiki</subtitle>
	<generator>MediaWiki 1.31.0</generator>
	<entry>
		<id>https://uww.wfgnationaltitle.com/index.php?title=Construction_Liens_in_North_Carolina&amp;diff=3718&amp;oldid=prev</id>
		<title>Davidjenkins: CSV import</title>
		<link rel="alternate" type="text/html" href="https://uww.wfgnationaltitle.com/index.php?title=Construction_Liens_in_North_Carolina&amp;diff=3718&amp;oldid=prev"/>
		<updated>2018-09-17T18:54:19Z</updated>

		<summary type="html">&lt;p&gt;CSV import&lt;/p&gt;
&lt;p&gt;&lt;b&gt;New page&lt;/b&gt;&lt;/p&gt;&lt;div&gt;==Overview==&lt;br /&gt;
&lt;br /&gt;
==Sources==&lt;br /&gt;
N.C. Gen. Stat. §§ 44A-7 et seq.&lt;br /&gt;
==Authorized Claimants==&lt;br /&gt;
Any person who performs or furnishes labor or professional design or surveying services or furnishes materials or furnishes rental equipment pursuant to a contract, either express or implied, with the owner of real property for the making of an improvement thereon shall, upon complying with the provisions of this Article, have a right to file a claim of lien on real property on the real property to secure payment of all debts owing for labor done or professional design or surveying services or material furnished or equipment rented pursuant to the contract. (N.C.G.S. § 44A-8)&lt;br /&gt;
==Lien Priority==&lt;br /&gt;
A claim of lien on real property granted by this Article shall relate to and take effect from the time of the first furnishing of labor or materials at the site of the improvement by the person claiming the claim of lien on real property. (N.C.G.S. § 44A-10) &lt;br /&gt;
==Notices and Registries==&lt;br /&gt;
==Filing Deadlines==&lt;br /&gt;
Claims of lien on real property may be filed at any time after the maturity of the obligation secured thereby but not later than 120 days after the last furnishing of labor or materials at the site of the improvement by the person claiming the lien. (N.C.G.S. § 44A-12(b)&lt;br /&gt;
==Enforcement Deadlines==&lt;br /&gt;
An action to enforce a claim of lien on real property may be commenced in any county where venue is otherwise proper. No such action may be commenced later than 180 days after the last furnishing of labor or materials at the site of the improvement by the person claiming the claim of lien on real property. (N.C.G.S. § 44A-13(a)&lt;br /&gt;
==Other==&lt;br /&gt;
&lt;br /&gt;
==Cross-References==&lt;br /&gt;
* [[North Carolina]]&lt;br /&gt;
* [[Construction Liens]]&lt;/div&gt;</summary>
		<author><name>Davidjenkins</name></author>
		
	</entry>
</feed>