Construction Liens in Wisconsin

From WFG Wiki
Revision as of 10:37, 17 September 2018 by Davidjenkins (talk | contribs) (CSV import)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)

Overview

Sources

Wis. Stat. §§ 779.01 et seq.

Authorized Claimants

Any person who performs, furnishes, or procures any work, labor, service, materials, plans, or specifications, used or consumed for the improvement of land, and who complies with s. 779.02, shall have a lien therefor on all interests in the land belonging to its owners. The lien extends to all contiguous land of the owner, but if the improvement is located wholly on one or more platted lots belonging to the owner, the lien applies only to the lots on which the improvement is located. (Wisc. Stat. Section 779.01(3))

Lien Priority

The lien provided in sub. (3) shall be prior to any lien which originates subsequent to the visible commencement in place of the work of improvement, except as otherwise provided by ss. 215.21 (4) (a), 292.31 (8) (i), 292.81 and 706.11 (1) and (1m). When new construction is the principal improvement involved, commencement is considered to occur no earlier than the beginning of substantial excavation for the foundations, footings or base of the new construction, except where the new construction is to be added to a substantial existing structure, in which case the commencement is the time of the beginning of substantial excavation or the time of the beginning of substantial preparation of the existing structure to receive the added new construction, whichever is earlier. The lien also shall be prior to any unrecorded mortgage given prior to the commencement of the work of improvement, if the lien claimant has no actual notice of the mortgage before the commencement. Lien claimants who perform, furnish, or procure any labor, services, materials, plans, or specifications for an improvement prior to the visible commencement of the work of improvement shall have lien rights, but shall have only the priority accorded to other lien claimants. (Wisc. Stat. 779.01(4))

Notices and Registries

Filing Deadlines

No lien under s. 779.01 shall exist and no action to enforce a lien under s.779.01 shall be maintained unless within 6 months from the date the lien claimant performed, furnished, or procured the last labor, services, materials, plans, or specifications, a claim for the lien is filed in the office of the clerk of circuit court of the county in which the lands affected by the lien lie…A lien claimant shall serve a copy of the claim for lien on the owner of the property on which the lien is placed within 30 days after filing the claim. A claim for a lien may be filed and entered in the judgment and lien docket, and action brought, notwithstanding the death of the owner of the property affected by the action or of the person with whom the original contract was made, with like effect as if he or she were then living. (Wisc. Stat. Section 779.06(1))

Enforcement Deadlines

No lien under s. 779.01 shall exist and no action to enforce a lien under s.779.01 shall be maintained …unless within 2 years from the date of filing a claim for lien an action is brought and summons and complaint filed…(Wisc. Stat. Section 779.06(1))

Other

Cross-References