Construction Liens in West Virginia
Contents
Overview
Sources
W. Va. Code §§ 38-2-1 et seq.
Authorized Claimants
Every person, firm or corporation who erects, builds, constructs, alters, removes or repairs any building or other structure, or other improvement appurtenant to any such building or other structure, or who alters or improves the real property whereon the same stands, or to which it may have been removed, or who provides services for any of the foregoing, under and by virtue of a contract with the owner for such erection, building, construction, alteration, removal or repair, either for an agreed lump sum or upon any other basis of settlement and payment, shall have a lien upon such building or other structure or improvement appurtenant thereto, and upon the interest of the owner thereof in the real property whereon the same stands, or to which it may have been removed, to secure the payment of such contract price or other compensation therefor. (West Virginia Code §38-2-1)
Lien Priority
A lien authorized and created by this article shall, when perfected, attach as of the date such labor, material, machinery or other necessary equipment shall have begun to be furnished, and shall have priority over any other lien secured by a deed of trust or otherwise which is created subsequent to such date. Each lien authorized and created by this article shall be subordinate to any other lien created by a deed of trust or otherwise which is duly recorded or otherwise perfected to constitute constructive notice prior to the date labor, material, machinery or other necessary equipment giving rise to such lien shall have begun to be furnished, notwithstanding the fact that some other lien authorized and created by this article may have priority over such other lien created by deed of trust or otherwise which is so recorded or otherwise perfected. (West Virginia Code §38-2-17)
Notices and Registries
Filing Deadlines
But the lien created and authorized by section one of this article shall be discharged from and after one hundred days from the completion of the contract unless, within the (that time period), the claimant of any such lien shall have perfected and preserved the same, as hereinafter provided in this article. (West Virginia Code §38-2-7)
Enforcement Deadlines
Unless an action to enforce any lien authorized by this article is commenced in a circuit court within six months after the person desiring to avail himself or herself of the court has filed his or her notice in the clerk's office, as provided in this article, the lien shall be discharged; but an action commenced by any person having a lien shall, for the purpose of preserving the same, inure to the benefit of all other persons having a lien under this article on the same property, and persons may intervene in the action for the purpose of enforcing their liens (West Virginia Code §38-2-34(a))