Overview

Sources

770 ILCS 60/0.01, et seq.

Authorized Claimants

Any person who shall by any contract or contracts, express or implied… with the owner of a lot or tract of land… to improve the lot or tract of land or for the purpose of improving the tract of land, or to manage a structure under construction thereon, is known under this Act as a contractor and has a lien upon the whole of such lot or tract of land… (770 ILCS 60/1 (a))

Lien Priority

No incumbrance upon land, created before or after the making of the contract for improvements under the provisions of this act, shall operate upon the building erected, or materials furnished until a lien in favor of the persons having done work or furnished material (hereinafter "lien creditor") shall have been satisfied… all previous incumbrances shall be preferred only to the extent of the value of the land at the time of making of the contract for improvements…(770 ILCS 60/16)

Notices and Registries

Filing Deadlines

No contractor shall be allowed to enforce such lien against or to the prejudice of any other creditor or incumbrancer or purchaser, unless within 4 months after completion, or if extra or additional work is done or labor, services, material, fixtures, apparatus or machinery, forms or form work is delivered therefor within 4 months after the completion of such extra or additional work… he or she shall either bring an action to enforce his or her lien therefor or shall file in the office of the recorder of the county in which the building, erection or other improvement to be charged with the lien is situated, a claim for lien…(770 60/7 (a))

Enforcement Deadlines

...Such claim for lien may be filed at any time after the claimant's contract is made, and as to the owner may be filed at any time after the contract is made and within 2 years after the completion of the contract, or the completion of any extra work or the furnishing of any extra labor, services, material, fixtures, apparatus or machinery, forms or form work thereunder... (770 ILCS 60/7)