Construction Liens in Virginia

From WFG Wiki

Overview

Sources

Va. Code ann. §§ 43-1 et seq.

Authorized Claimants

All persons performing labor or furnishing materials of the value of $150 or more, including the reasonable rental or use value of equipment, for the construction, removal, repair or improvement of any building or structure permanently annexed to the freehold, and all persons performing any labor or furnishing materials of like value for the construction of any railroad, shall have a lien, if perfected as hereinafter provided, upon such building or structure, and so much land therewith as shall be necessary for the convenient use and enjoyment thereof, and upon such railroad and franchises for the work done and materials furnished…(VA Code § 43-3 (A.))

Lien Priority

No lien or encumbrance upon the land created before the work was commenced or materials furnished shall operate upon the building or structure erected thereon, or materials furnished for and used in the same, until the lien in favor of the person doing the work or furnishing the materials shall have been satisfied; nor shall any lien or encumbrance upon the land created after the work was commenced or materials furnished operate on the land, or such building or structure, until the lien in favor of the person doing the work or furnishing the materials shall have been satisfied. (VA Code § 43-21)

Notices and Registries

Filing Deadlines

A general contractor, or any other lien claimant under §§ 43-7 and 43-9, in order to perfect the lien given by § 43-3, provided such lien has not been barred by § 43-4.01 C, shall file a memorandum of lien at any time after the work is commenced or material furnished, but not later than 90 days from the last day of the month in which he last performs labor or furnishes material, and in no event later than 90 days from the time such building, structure, or railroad is completed, or the work thereon otherwise terminated. The memorandum shall be filed in the clerk's office in the county or city in which the building, structure or railroad, or any part thereof is located…(VA Code § 43-4)

Enforcement Deadlines

No suit to enforce any lien perfected under §§ 43-4, 43-5 and 43-7 to 43-10 shall be brought after six months from the time when the memorandum of lien was recorded or after sixty days from the time the building, structure or railroad was completed or the work thereon otherwise terminated, whichever time shall last occur; provided, however, that the filing of a petition to enforce any such lien in any suit wherein such petition may be properly filed shall be regarded as the institution of a suit under this section; and, provided further, that nothing herein shall extend the time within which such lien may be perfected. VA Code § 43-17)

Other

Cross-References